← My Water  ·  Print / save as PDF

NORTH SIDE ADAMS D

Structure dossier · WDID 5800802 · 1 · TODD CREEK · DWR record

Where this page's figures come from

Generated 2026-08-28 01:24 by Hydrohistorian. Sources: DWR HydroBase snapshot HydroBase_CO_20260707 (history) + CDSS REST (current), USGS NWIS cross-checks. Engine v0.5.0 (a1c9146) — every figure regenerates from this named code version and data image.

Where it sits

Location as DWR records it. Faint dots are the neighbouring water; click any to open it.

Which of its rights are out of priority?

Not computable for this structure: this structure is not on the modelled flow network, so no reference gage can honestly stand in for it.

Where it sits in line

Priority 1935-06-01753rd most senior of the 3097 structures with decreed rights in this water districtDWR's administrative subdivision of a river basin; the unit calls are usually stated in..

Under prior appropriationColorado's rule for sharing water: first in time, first in right. Age decides, not proximity or need., everything ahead of it in this line is satisfied in full before it receives any water. Immediately ahead: COULTON CREEK DITCH (1934-07-01). Immediately behind: SOUTH SIDE ADAMS D (1935-06-01).

Decreed rights (1)

Admin noDWR's numeric encoding of a water right's seniority. Smaller is more senior; the integer part counts days from 1849-12-31 to the date that ranks the right. AppropriatedWhen water was first put to beneficial use. It sets seniority unless a prior adjudication date is later. AdjudicatedWhen the water court confirmed the right. A use decreed in 1975 was not a decreed use in 1955, however old the appropriation is. AbsoluteA right actually put to use, as opposed to conditional -- a placeholder for a use not yet made. ConditionalA right reserving a place in line for a use not yet made; it must be diligently pursued or it lapses. UnitsUsesWhat the court said this water may be used for -- irrigation, municipal supply, augmentation and so on.Case
39254.311971935-06-011964-03-30 0.340.0 CIRR 12

Recorded use (last 15 years on record)

In a median year this structure has a recorded diversion of 22 AF. Its most recent year on record, 2025, came in at 0 AF — 0% of that, and 1st lowest of the 15 years with a recorded volume.

YearDiverted (AFA volume: one acre covered a foot deep, about 326,000 gallons -- roughly a suburban household's outdoor use for a year.)Compared with its own recordDays recordedPeak (cfs)
2009 31 10th lowest of 15 · 141% of median 43 0.5
2010 22 8th lowest of 15 · 100% of median 55 0.4
2011 37 12th lowest of 15 · 168% of median 45 0.5
2012 8 6th lowest of 15 · 36% of median 17 0.2
2013 21 7th lowest of 15 · 96% of median 33 0.4
2014 105 15th lowest of 15 · 477% of median 76 1.2
2015 103 13th lowest of 15 · 468% of median 86 0.8
2016 103 13th lowest of 15 · 468% of median 81 1.5
2017 23 9th lowest of 15 · 104% of median 40 0.3
2018 31 10th lowest of 15 · 141% of median 105 0.4
2019 0 1st lowest of 15 · 0% of median 4 0.0
2021 0 1st lowest of 15 · 0% of median 6 0.0
2022 0 1st lowest of 15 · 0% of median 2 0.0
2023 0 1st lowest of 15 · 0% of median 2 0.0
2025 0 1st lowest of 15 · 0% of median 1 0.0

How good is our record of it?

Grade B (7/10 points) — the components below are the finding; the letter alone is not.

The rubric, component by component
CheckStateDetail
identity complete name, type, and water source all on file
decreed rights on file 1 right(s), seniority decoded
diversion record present 2290 measured days; currency unknown (no data-coverage date to compare against)
record continuity sparse 19% of the irrigation seasons in 1969-2025 carry measured days
published-record stability stable no upstream revisions recorded against this structure

Advisory reading aid on public data — not an administrative or legal conclusion, not a title opinion, and not a substitute for DWR administration or an engineer's analysis. Methodology review status is disclosed at hydrohistorian's basin pages.